image

image
image
image
harmonic mitigation, harmonic surveys, harmonic filters, harmonic analysis, harmonic studypower factor correction, pfc servicing, pfc surveyG5/4, G54, G5/4 survey, G5/4 summary, G5/4 compliancePQM Ltd, power quality services,g5/4 surveys, G54 survey, pf surveys,harmonic modelling, system modelling, G5/4pfc servicing, ups servicing, active filter servicing, harmonic filter servicing


 

The BLUEWAVE active filter is here.

Electricity Association Document G5/4-1...

 



Background
As with all other harmonic regulations world-wide, G5/4 was written to ensure that levels of harmonic current in the Public Electricity supply system do not give rise to problems for connected users. Previously in the UK the harmonic distortion was regulated by Electricity Council Recommendation G5/3 (1976) and this still remains in place today for existing supplies. Parts of G5/3, however, were made obsolete by the introduction of BSEN61000-3-2 which covers supplies and equipment up to 16A, so a replacement was required.

Measurements
To ensure G5/4 compliance, measurements must be taken at the Point of Common Coupling with other users (usually the energy metering point - for a customer with their own transformer this will be 11kV). Measurements are generally needed for Stage 2 and Stage 3 assessment to give background distortion. Responsibility for the background tests lies with the DNO (Distribution Network Operator) company, although the customer may be asked to assist.

Measurements must be taken over a seven (7) day period to cover peak distortion periods (Saturday & Sunday evening), unless the process will not operate over these periods.

The Prospective Fault level of the supply is a crucial element as it determines the current distortion limits; the levels stated in the document's tables should be scaled according to the fault level. All the stated figures are based on 10MVA for 400V supplies and 100MVA for 11kV supplies. Where a system has a lower fault level (e.g. 50MVA for an MV user) the allowable 5th harmonic current is halved from 3.9 to 1.95A.

Voltage distortion measurements are extremely important as the majority of cases will be decided on the THD(V) figure for the supply.

For the purpose of the study (G5/4 compliance) short duration harmonic generating loads such as Soft Starter Drives are exempt (assuming they comply with P28 flicker regulation).

Stage 1
This stage applies to all supplies between 16 and 75A, and connections at 400A. A 10MVA fault level is assumed and allows for up to a maximum of four harmonic generators to be connected to the supply. The levels of current distortion must not exceed the figures given in Table 7.

Where these are exceeded then a THD(V) of no more than 5% is allowed. Typical sizes of drives that can be connected based on typical drive spectra (Gambica G5/4 Guide 2001) are:

6 pulse - 30kW (limited by 5th harmonic current)
12 pulse - 300kW (limited by 23rd harmonic current)

Where the current and voltage distortion figures have been exceeded the assessment must move to Stage 2 .

Stage 2
This stage applies to those exceeding Stage 1 levels and those having a point of common coupling below 33kV. At this stage the NOC is obliged to measure background distortion and inform the user of the fault level.

Total drive loads of the following sizes can be connected without further assessment:

6 pulse - 130kVA
12 pulse - 250kVA

If the level of background distortion is less than 75% of the maximum THD(V) allowable, then Table 12 should be used.

Excluding 3rd and 5th, any two orders (up to 19th) may exceed the values by 10% or 0.5A, whichever is greater. Above 19th they may exceed by 10% or 0.1A whichever is greater.

Where these figures have been exceeded then the voltage distortion levels given by Table 11 should be used for THD(V) and levels of 5th harmonic voltage distortion (other harmonic order limits are as per draft IEC61000-2-12).

Stage 3
This assessment applies to circumstances which fall outside the scope of stages 1 and 2. It is applicable to any non-linear equipment that has a PCC of 33kV and above.

Harmonic voltages at the PCC are assessed on an impedance model of the network, and possible resonance points. The modelling and metering is the sole responsibility of the DNO.

For 33kV and above, the assessment should take into account the effects of harmonic distortion on connected lower voltage networks.

Circumstances for Exceeding G5/4
Where the voltage distortion levels are exceeded, the DNO will give a conditional connection agreement which may need mitigation measures. However the final decision on whether connection is possible is left with the DNO (judge and jury).

Where circumstances are uncertain (possible resonance) then the DNO may give a conditional connection where remedial measures can be implemented within a reasonable time-scale.

In exceptional circumstances, where the site to be connected is remote from other customers, it may be considered at Stage 2 with computability levels appropriate to the system voltage.

image

 



 

 

 

 

 

 

 

 

 
image
image
  image